In February, we held the groundbreaking for a 2000 module solar PV installation for our American HQ in El Segundo, Calif. We had some honored guests at the groundbreaking, including HRH Prince Andrew, The Duke of York.
Once completed, the system is expected to generate approximately 917,000 kWh per year and reduce carbon emissions by 642,000 pounds annually, which represents at least 15% of the site’s emissions. You can find more details in the press release .
We have had some delays that I gather impact many building projects, and most of the work since has been on the foundation. so there has been little to see. But now, at last, panels are starting appear on the roof and there is a camera in place monitoring progress.
Click on "animation viewer" and you will see progress from the current day. Even better, select "previous week" in the animation window to see the progress over the past week. I feel like a kid with a new toy!
When the roof is done, the camera will be rotated to cover the parking lot where the tracking panels will be placed. At the moment, the vendor is working on foundation there, so not much to see yet, but I will add the occasional post when there is some especially good progress to share.